October 30, 2026
Consarc Corporation October Construction Update
October Recap
The fall season has quickly descended upon South Jersey. Even though the temperatures are dropping and the days are shortening, October hasn't slowed down one bit for Consarc. Our facility expansion is growing closer to completion, and with how busy we’ve been, we are counting down the days until we can move in and begin utilizing the new space.
This month, contractors completed all of the necessary under-slab electrical work that will be hidden under the facility floor. Completion of this milestone means that the concrete floor can finally be poured, which opens the next phase of construction. Other trades will be able to work as sections of floor dry, cure, and are able to support equipment for the first time.
Bathrooms in the facility are nearing completion, with just a few functional elements like ceiling and floor tile left to install. The final work on plumbing and electrical work can be finished once the tiles are installed.
Finally, structural steel roof beams are being fabricated, and overhead bridge cranes are scheduled to arrive next week. They can be installed once the floor is cured and ready to support the heavy equipment necessary to raise them to their final elevation.
Check back each month to see how construction is progressing!